Weekly Idaho St Construction Update For 07/11/2022



The plan for the week is to install service lines from Sebree to Glendale today and tomorrow. They will be pulling concrete for ADA ramps and graveling them in at the intersection of Bannack and Idaho. Concrete crew should be in this week to begin work on ADA ramps. Hopefully we can get the street cut down between Bannack and Glendale and get it graveled this week pending getting information to build a GPS model for our grader from the engineer. Let me know if you have any questions.




Kipp Shumway

Mungas Company

406-860-8155

P.O. Box 1390

Anaconda, MT 59711