Idaho Street Construction Update Week Of 07/18/2022
top of page

Idaho Street Construction Update Week Of 07/18/2022



The plan is to finish installing services on Bannack from Montana to Idaho. We will then install the services on Idaho from Glendale to Bannack. We should have Bannack graveled and open by the end of this week. As far as Idaho goes the engineers messed up the data for me to use to make my GPS model so I just got that today. Hopefully we can get a quick turn around on the model building and we can get to grading the road between Center and Bannack. Concrete guys will be there Wednesday and should get most of the ADAs done. We will post sidewalk closed signs as they are curing. Let me know if you have any questions.



Kipp Shumway

Mungas Company

406-860-8155

P.O. Box 1390

Anaconda, MT 59711



86 views0 comments

Recent Posts

See All
bottom of page