Plan for the week is to do the dig out of the soft spot on Idaho from Helena to Center and get it filled back in, graveled and opened back up. Paving will be happening on Idaho and Bannack this week and the streets will be opened back up as soon as the asphalt is cool enough to drive on. The last of the storm drain will be installed on Idaho. We are still waiting on data from the engineer for our GPS to get the street subgrade cut so we can gravel it. I'm hoping to have it this week. As soon as we get it we ill get the last two blocks of Idaho cut to subgrade and graveled. Work on the Fairground will also begin this week and should be installed by the end of next week.