Construction Look Ahead:

MDT and Helena Sand and Gravel anticipate working on the following, weather dependent:



Week of April 24:


  • One lane of the bridge over the railroad and removing guardrail to prep for bridge surface replacement.

  • Traffic: single-lane bridge closures with temporary traffic lights.

  • Concrete work: continuing sidewalk and curb removal and replacement along East Helena Avenue.

  • Traffic: daytime single-lane closures along East Helena Avenue. Both lanes open at night. Side streets closed at East Helena Avenue intersections. Businesses along side streets will have access from East Center Street.

  • Pedestrians: partial sidewalk closures day and night while concrete cures.




Week of May 1:


  • Street driveway tie-ins along East Helena Avenue.

  • Continue one lane of bridge work and begin bridge wall repair.

  • Traffic: single-lane bridge closures with temporary traffic lights.

  • Concrete work: begin to move from East Helena Avenue down South Atlantic Street with some sidewalk removal at intersection corners.

  • Traffic: Atlantic Street is expected to have similar traffic control measures as East Helena Avenue. Updates will be issued within the next few weeks.

  • Pedestrians: partial sidewalk closures day and night while concrete cures.