Construction Look Ahead:
MDT and Helena Sand and Gravel anticipate working on the following, weather dependent:
Week of April 24:
One lane of the bridge over the railroad and removing guardrail to prep for bridge surface replacement.
Traffic: single-lane bridge closures with temporary traffic lights.
Concrete work: continuing sidewalk and curb removal and replacement along East Helena Avenue.
Traffic: daytime single-lane closures along East Helena Avenue. Both lanes open at night. Side streets closed at East Helena Avenue intersections. Businesses along side streets will have access from East Center Street.
Pedestrians: partial sidewalk closures day and night while concrete cures.
Week of May 1:
Street driveway tie-ins along East Helena Avenue.
Continue one lane of bridge work and begin bridge wall repair.
Traffic: single-lane bridge closures with temporary traffic lights.
Concrete work: begin to move from East Helena Avenue down South Atlantic Street with some sidewalk removal at intersection corners.
Traffic: Atlantic Street is expected to have similar traffic control measures as East Helena Avenue. Updates will be issued within the next few weeks.
Pedestrians: partial sidewalk closures day and night while concrete cures.