top of page
Writer's pictureJeremy Crawford

Idaho Street Construction Update For The Week Of 07/05



Plan for the week is to get the intersection of Glendale and Idaho put back together and opened up. We will be installing services on the block of Idaho, between Center and Bannack. There will be another crew working on installing storm drain structures in the intersection of Bannack and Idaho. Testing will be taking place into the Bannack intersection for water lines as well. Once those pass we can install the services on Bannack between Washington and Idaho and up to Montana St. Concrete ADA corners should be starting to get poured next week.




153 views0 comments

Comments


bottom of page