Idaho Street Construction Update For Week Of 08/23/2022

Email from Mungas Construction:

So plans for the week are, prepping for curb on ID street today. Curb pouring will begin tomorrow and they are planning on finishing on Thursdayish. The entire stretch of ID St will be closed for the week. The new curb will need time to cure before we can kick traffic back on to it. The rest of the week will be spent doing cleanup and punch list items around town. Pavement prep next week.